| N.P. Malyshev | EFFICIENCY OF THE INNOVATION TECHNOLOGY TRANSFER FROM GERMANY FOR PROCESSING SOLID DOMESTIC WASTE IN EAST KAZAKHSTAN |
| D. Serikbaev East-Kazakhstan State Technical University, Ust-Kamenogorsk, Kazakhstan |
In the article some aspects of efficiency of the project transfer of technology from Germany on processing solid domestic waste (SDW) in East Kazakhstan are considered. The similar engineering and technology of processing is practically absent in Kazakhstan.
The project pursues the purpose involving in an economic revolution of city and region in the whole products of useful fractions (secondary raw material) processing SDW by construction of a factory on processing SDW in Ust-Kamenogorsk by capacity up to 100,0 thousand tons per one year.
The purchase of a unique complex an innovation technique disposal plant from Germany by productivity up to 100, 0 thousand tons per one year is supposed. Common settlement cost (volume of the investments) all components of the project (without the account of inflation) makes 43 079 527,75 EU. Including cost of the equipment and delivery it from Germany - 27 700 000,00 EU.
The most important indicators of the project are:
The settlement financial stability of the project will make not less than 86, 0%. The period of account of integrated parameters of the project is 96 months. The discount
rate on KZT is accepted at a level of the official refinancing rate, established RK NB from
01.10.08 of year. The discount rate on EU is accepted at a level of the refinancing rate, authorized ECB (www.prime-tass.ru ). The account is made in view of inflation in 2008-2010 years at a level - 8,5-9,5%% per one year.
Planned date started of the project is 01.03.2009. The interest rate under the credit in EU 3,0% annual. Common investment cost, (the capital expenses in view of inflation) make - 44 999 820,91 EU or 7 784 567 372,93 KZT for the term of 72 months.
The basic source of financing of the project is the credit of foreign bank – Savings Bank of Russia in volume 45000000,0 UR under 3,0% annual rates. The credit resources are directed on realization of construction of the basic objects of a complex, objects of an engineering infrastructure, purchase and installation (starting-up and adjustment works) foreign (Germany) of the process equipment on processing SDW. The parity of cost of the equipment and civil and construction works in the project makes 65:35, that characterizes the project as transfer of innovation of technology in our area.
The maximal risk value: risks decrease of the volumes or rates of processing SDW (36,95%); reduction of the market prices on production of the project (22,17%); decrease of the volumes of services on processing SDW on contractual conditions (19,95%); the current lack of money resources (17,73%); acts of nature (2,46%).
The total, settlement risk will make ours of the project is 39,3%, that will quite be coordinated to specificity of the projects sold in civil-municipal sector of the regional economy.
Thus, as have shown accounts of the author, it is possible with the large reliance to ascertain, that the realization of the investment project in which basis lays transfer of German technology on processing SDW by capacity up to 100,0 thousand tons per one year is rather perspective from the point of view of commercial and its budget efficiency.